What will a landscape contractor charge extra for once they start digging?

Extras often come from unforeseen conditions or vague contracts. Once digging begins, contractors may find irrigation lines, old concrete, buried debris, or poor soil that require additional work. Without a clear agreement, these costs can be added to your bill. Common extras include hauling excess dirt, adding drainage solutions, or installing upgraded irrigation parts. In Utah, rocky soil is a frequent surprise that drives up excavation costs. The key is to review your contract for how “unforeseen conditions” are defined and priced. Ask the contractor to specify unit costs (per cubic yard of soil, per linear foot of pipe) so you’re not blindsided later. Also ask whether they’ll seek approval before charging for extras. Reputable contractors document change orders in writing and get your signature before proceeding. While some extras are unavoidable, many can be anticipated in advance by doing a thorough site walk with the contractor before work begins.